Proposed works

These works form part of the Historic Bridge Maintenance Programme.

The works are expected to include:

  • Extensive repair of missing and damaged stonework including masonry replacement and refacing (above and below water level), repointing, scour repairs and carriageway resurfacing.
  • Arch strengthening and repairs to the tie-bars.

Missing and damaged stonework

Binton bridge damage to arch

Binton Bridge missing brickwork

Binton Bridge damaged stonework

These works will maintain the highway structure function for both pedestrians and vehicular traffic which in turn will increase the service life of the structure and reduce future maintenance costs.

Site works have commenced on Monday 2 October 2023 and are due to be completed 7 June 2024.

Traffic Management Programme

Traffic management type Duration Date start Date end
2-way temporary lights (cleared for marathon 21/4/24) 58 days

Sat 23/3/24

Sun 19/5/24

Road closure (with pedestrian access) 4 days Mon 20/5/24 Thur 23/5/24
Road closure (no pedestrian access) 1 day

Fri 24/5/24

Fri 24/5/24

2-way temporary lights 14 days

Sat 25/5/24

Fri 7/6/24

Fully open 0 days Fri 7/6/24 Fri 7/6/24

Please note these times and durations are subject to review as the works are progressed.


Progress photographs

P1 scaffold foundation

P2 scaffold base

P3 upstream scaffold

P4 downstream scaffold

Navigation arch stone condition

Repointing

Temporary support

Temporary support 2

Shuttering support

Flood debris

Flood debris january 24

Flood debris january 24

Arch stone cut out

Arch stone removed

Arch replacement stone

Flood debris removal

Flood debris february 24

Reconstructed arch ring

Reconstructed arch ring 2

Binton Bridge repairs 1.3.2024

Binton Bridge repair 1 March 2024

Repairs to Binton Bridge 1 March 2024

Repairs to Binton Bridge 1 March 2024

May 2024 progress 1

May 2024 progress 2

May 2024 progress 3

May 2024 progress 4

May 2024 update 5

May 2024 update final

 