Updates
Update: 7 February 2025
Coton Road improvements - Balfour Beatty Living Places (BBLP) are in negotiations with WCC Network Management to book road space for the planned works. The works, which involve the introduction of spiral road markings to the Coton Road roundabout to improve traffic flow, are likely to be undertaken in early 2025.
Leicester Road gyratory - This scheme is planned to replace the existing Leicester Road gyratory with a new signalised roundabout to improve traffic flow along Nuneaton’s ring road. The planning application for the scheme was submitted at the end of October 2024 and the plans are now available for public review. Due to the location of the scheme and the number of stakeholders involved, the commencement of site works will be determined at the detail design stage subject to planning approval and acquisition of certain land.

The cleared scrub land on Wheat Street
Wheat Street junction - The scheme involves changing the existing three-legged Wheat Street junction with Vicarage Street to a new four-legged layout and will provide easier access to Nuneaton’s ring road from Bond Gate to ease traffic congestion in the town centre. Critical land acquisitions have been agreed and the detailed design is progressing well. It is intended put the construction works up for tender in early 2025 with the intention to commence construction in summer 2025. The scrub land on the north side of Wheat Street and vegetation on the east side Justice Walk Car Park was cleared in November following completion of ecological surveys.
Update: 22 January 2025
Coton Road Improvements – Balfour Beatty Living Places (BBLP) are in negotiations with WCC Network Management to book road space for the planned works. The works, which involve the introduction of spiral road markings to the Coton Road roundabout to improve traffic flow, are likely to be undertaken in early 2025.
Leicester Road Gyratory – This scheme is planned to replace the existing Leicester Road gyratory with a new signalised roundabout to improve traffic flow along Nuneaton’s ring road. The planning application for the scheme was submitted at the end of October 2024 and the vetting process has been successfully completed. The plans are available for public review. Due to the location of the scheme and the number of stakeholders involved, the commencement of site works will be determined at the detail design stage subject to planning approval and acquisition of certain land.
Wheat Street Junction – This scheme involves changing the existing 3 legged Wheat Street junction with Vicarage Street to a new 4 legged layout and will provide easier access to Nuneaton’s ring road from Bond Gate to ease traffic congestion in the town centre. Critical land acquisitions have been agreed and the detail design is progressing well. It is intended put the construction works up for tender in early 2025 with the intention to commence construction in Summer 2025. The scrub land on the north side of Wheat Street and vegetation on the east side Justice Walk Car Park was cleared in November following completion of ecological surveys.
Update: 8 January 2025
Coton Road Improvements – Balfour Beatty Living Places (BBLP) are in negotiations with WCC Network Management to booking road space for the planned works. The works, which involves the introduction of spiral road markings to the Coton Road roundabout to improve traffic flow, are likely to be undertaken in early 2025.
Leicester Road Gyratory – The scheme is to replace the existing gyratory at Leicester Road with a new signalised roundabout. Due to the location of the scheme and the number of stakeholders involved, the commencement of site works will be determined at the detail design stage subject to planning approval and certain land acquisitions. The planning application for the scheme was submitted at the end of October 2024 and is currently being reviewed by WCC Planning officers and will be made public shortly.
Wheat Street Junction – The scheme involves changing the existing 3 legged Wheat Street junction with Vicarage Street to a new 4 legged layout and will provide easier access to Nuneaton’s ring road from Bond Gate to ease traffic congestion in the town centre. Critical land acquisitions have been agreed and the detail design is progressing well. It is intended put the construction works up for tender in early 2025 with the intention to commence construction in Summer 2025. The scrub land on the north side of Wheat Street and vegetation on the east side Justice Walk Car Park was cleared in November following completion of ecological surveys.
Update: 11 December 2024
Coton Road Improvements – The scheme involves the introduction of spiral road markings to the Coton Road roundabout to improve traffic flow. Balfour Beatty Living Places (BBLP) is to ascertain in negotiations with WCC Network Management when road space for the planned works will be available. The works are likely to be undertake early 2025.
Leicester Road Gyratory – The scheme is to replace the existing gyratory Leicester Road with a new signalised roundabout. Due to the location of the scheme and the number of stakeholders involved, the commencement of site works will be determined at the detail design stage subject to planning approval and certain land acquisitions. The planning application for the scheme was submitted at the end of October 2024 and is currently being reviewed by WCC Planning officers and will be made public shortly.
Wheat Street Junction – The scheme involves changing the existing 3 legged Wheat Street junction with Vicarage Street to a new 4 legged layout and will provide easier access to the ring road from Bond Gate to ease town centre traffic congestion. Critical land acquisitions have been agreed and the detail design is progressing well. It is intended put the construction works up for tender in early 2025 with the intention to commence construction in Summer 2025. The scrub land on the north side of Wheat Street and vegetation on the east side Justice Walk Car Park was cleared in November following completion of final ecological surveys.
Update: 26 November 2024
Currently WCC maintenance contractor is in negotiations with WCC Network Management to ascertain when road space for the planned works will be available. The scheme involves the introduction of spiral road markings to the Coton Road roundabout to improve traffic flow. The works are likely to be undertake early 2025.
Leicester Road Gyratory – The scheme is to replace the existing gyratory Leicester Road with a new signalised roundabout. Due to the location of the scheme and the number of stakeholders involved, the commencement of site works will be determined at the detail design stage subject to planning approval and certain land acquisitions. The planning application for the scheme was submitted at the end of October 2024 and is currently being reviewed by WCC Planning officers and will be made public shortly.
Wheat Street Junction – The scheme involves changing the existing 3 legged Wheat Street junction with Vicarage Street to a new 4 legged layout and will provide easier access to the ring road from Bond Gate to ease town centre traffic congestion. Critical land acquisitions have been agreed and the detail design is progressing well. It is intended put the construction works up for tender in early 2025 with the intention to commence construction in Summer 2025. The scrub land on the north side of Wheat Street and vegetation on the east side Justice Walk Car Park was cleared in November following completion of final ecological surveys.
Update: 18 November 2024
Coton Road Improvements – The scheme involves the introduction of spiral road markings to the Coton Road roundabout to improve traffic flow. Currently WCC maintenance contractor is in negotiations with WCC Network Management to ascertain when road space for the planned works will be available.
The works are planned to be undertake by WCC’s maintenance contractor during the current financial year.
Leicester Road Gyratory – The planning application for the scheme design to replace the existing gyratory with a new signalised roundabout was submitted at the end of October 2024 and is currently being reviewed by WCC Planning officers for completeness and accuracy.
Due to the location of the scheme and the number of stakeholders involved, the commencement of site works will be determined at the commencement of the detail design phase, subject to planning approval and acquisition of certain lands.
Wheat Street Junction – The scheme is required to provide easier access to the ring road from Bondgate to ease town centre traffic congestion. The design is progressing well and involves changing the existing 3-legged Wheat Street junction with Vicarage Street to a new 4-legged layout. It is planned the design will be completed in early 2025 and the main site works commenced in Summer 2025. In advance of the main works, the scrub land on the north side of Wheat Street at its existing junction with Vicarage Street and vegetation on the east side Justice Walk Car Park will be cleared in November and following completion of seasonal ecological surveys to ensure no existing habitats are affected.
Update: 30 October 2024
Coton Road Improvements - The scheme involves the introduction of spiral road markings to the Coton Road roundabout to improve traffic flow and the works are planned to be undertaken by WCC’s maintenance contractor during the current financial year. The contractor is currently in negotiations with WCC Network Management and reviewing to ascertain when road space for the planned programme of works will be available.
Wheat Street Junction - The scheme is required to provide easier access to the ring road from Bondgate to ease town centre traffic congestion. The design is progressing in accordance with the programme and involves changing the existing 3-legged Wheat Street junction with Vicarage Street to a new 4-legged layout. The main site works are planned for Summer 2025. In advance of the main works, the scrub land on the north side of Wheat Street at the existing Vicarage Street junction will be cleared over winter and following seasonal ecological surveys to ensure no existing habitats are affected.
Leicester Road Gyratory - The planning application scheme design to replace the existing gyratory with a new signalised roundabout is continuing without delay and the planning application is expected to be made in Autumn 2024. Due to the location of the scheme and the number of stakeholders involved the commencement of site works will be determined following planning approval and acquisition of certain properties.
Update: 16 October 2024
Coton Road Improvements – The scheme involves the introduction of spiral road markings to the Coton Road roundabout to improve traffic flow and the works are planned to be undertaken by WCC’s maintenance contractor during the current financial year. The contractor is currently in negotiations with WCC Network Management with a view to ascertain when road space for the planned programme of works will be available.
Wheat Street Junction – The scheme is required to provide easier access to the ring road from Bondgate to ease town centre traffic congestion. The design is progressing in accordance with the programme, which involves changing the existing 3 legged Wheat Street junction with Vicarage Street to a new 4 legged layout. The main site works are planned for Summer 2025 but in advance of the main works, the scrub land on the north side of Wheat Street at the existing Vicarage Street junction will be cleared over winter and following seasonal ecological surveys to ensure no existing habitats are affected.
Leicester Road Gyratory – The planning application scheme design to replace the existing gyratory with a new signalised roundabout is continuing without delay and the planning application is expected to be made in Autumn 2024. Due to the location of the scheme and the number of stakeholders involved the commencement of site works will be determined following planning approval and acquisition of certain properties.
Update: 30 September 2024
Coton Road Improvements – The works are planned to be undertaken within the current financial year by WCC’s maintenance contractor. The scheme involves the introduction of spiral road markings to the Coton Road roundabout to improve traffic flow. WCC Network Management and the contractor are currently reviewing the planned programme of works to ascertain when road space for the works can be secured.
Wheat Street Junction – The design which involves changing the existing 3 legged Wheat Street junction with Vicarage Street to a 4 legged is progressing in accordance with the programme. The scheme is required to provide easier access to the ring road from Bondgate to ease town centre traffic congestion. The scrub land on the north side of Wheat Street at the existing Vicarage Street junction will be cleared following the bird nesting season ecological surveys of the site have been undertaken to ensure there are no habitats. The main site works is planned for Summer 2025.
Leicester Road Gyratory – The planning application scheme design to replace the existing gyratory with a new roundabout is continuing without delay and the planning application is expected to be made in Autumn 2024. Due to the location of the scheme and the number of stakeholders involved the commencement of site works will be determined following planning approval.
Archaeological trial trenching in the Nuneaton and Bedworth Borough Council car parks off Regent Street (by the Empire Gym) have been completed and the car parks reopened.
We thank you for your patience and understanding regarding any inconvenience these works may have caused.
For details on road closures view the one.network website.