Programme updates: Warwick and Leamington
Below is a summary of Section 278 (s278) programmes to date in Warwick and Leamington:
Gallows Hill, Warwick | |
---|---|
Activity | Additional work at the new Fusiliers Way junction to install new signage |
Developer | L&Q and Countryside |
Contractor | Fitzgerald Contractors |
Status of works | Under construction |
Start date planned | 3 March 2025 |
Completion date |
28 March 2025 plus from 26 to 28 April 2025 to install new signage. Further information can be found on the Gallows Hill, Warwick 2025 update page. |
C5 Orton Road, Warton (Warton Allotments) | |
---|---|
Activity | Carriageway wideninging and road markings, new parking bays, new footpaths and construction of new access |
Developer | Countryside Partnerships |
Contractor | Lambes Construction |
Status of works | TBC |
Start date planned | TBC |
Completion date | TBC |
B4413 Longford Road (Wilsons Lane) Exhall | |
---|---|
Activity | Carriageway resurfacing and road markings, new footpaths and construction of new access |
Developer | Barwood Capital |
Contractor | Conlon Construction |
Status of works | Under construction |
Start date planned | 13 January 2025 |
Completion date | TBC |
D7069 Glasshouse Lane East Roundabout and Cycleway | |
---|---|
Activity | Construction of new roundabout, footpaths and cyclepaths with associated street lighting and road markings |
Developer | Vistry Homes |
Contractor | TBC |
Status of works | TBC |
Start date planned | TBC |
Completion date | TBC |