Programme updates: Rugby
Houlton Way/Hillmorton Lane Junction, Rugby - March 2025 update
Construction works to revoke some banned vehicular movements at Houlton Way/Hillmorton Lane Junction, Rugby will commence on Monday 3 March. To clarify, we will be using 4 way temporary traffic signals and there will be temporary pedestrian crossing points provided.
The duration is likely to be ten days.
B4429 Coventry Road Symmetry Park | |
---|---|
Activity |
Upgrading the existing M45/A45 Thurslaston interchange, realignment of B4429 Coventry Road and new signalised junction into Symmetry Park |
Developer | Tritax Symmetry |
Contractor | Winvic Construction Ltd |
Status of works | Contractor mobilisation |
Start date planned | 6 January 2025 |
Completion date | TBC |
A426 Rugby/Dunchurch/Barby Road - Barby Road junction improvements | |
---|---|
Activity |
The works consist of widening the B4429 Ashlawn Road on the eastbound approach to the junction with Barby Rd and Onley Lane, to create two lanes. The junction will also be converted to a signalised junction, with new controlled crossings for pedestrians introduced. The scheme also involves installing new highway drainage, traffic signs, street lighting, kerbing, footway/cycleway and new road markings. Existing cycleway provision will be enhanced and minor realignment of Route 41 will be required. Resurfacing of the junction will also be carried out. |
Developer | David Wilson Homes |
Contractor | To be confirmed |
Status of works | The s278 technical review is 90% complete. The scheme is to be tendered by March. |
Start date planned | Spring 2025 TBC |
Completion date | Works will take approximately 16 weeks to complete. |
Cock Robin Roundabout, Rugby - Scheme Complete July 2024
Scheme Overview - The works consisted of a single toucan crossing on Ashlawn Road and a dual toucan crossing on Dunchurch Road arms of the Cock Robin Roundabout.